JPR Studio Project | Timeline & Funding Update

Dec 14, 2015

PROJECT TIMELINE:

  • October, 2016: Design work completed
  • November, ,2016: Construction bidding and selection of general contractor
  • February, 2017: Construction begins
  • December, 2017: Construction completed
  • January, 2018: Move completed
  • March, 2018: Grand Opening

FUNDING OVERVIEW:

  • $2,700,000: Total Project Budget
  • $1,200,000: Dedicated funds raised for project -- Thanks to the¬†JPR Foundation, the Collyer Hitchcock Fund of the Oregon Community Foundation, the Fred W. Fields Fund of the Oregon Community Foundation, the Gordon Elwood Foundation, the Carrico Family Foundation and the generous friends of JPR
  • $1,400,000: Southern Oregon University capital financing -- Approved by Oregon Higher Education Coordinating Commission
  • $100,000: Remaining funds needed to complete project
Tags: